Update – April 2008 ongoing renovation of the gite

WHERE WE ARE UP TO – APRIL 2008.

 

Since our last update in February, we have completed many of the items we hoped to and are nearing the end of the renovation of the Gite / Holiday Cottage – which will receive its first guests in a couple of weeks:

 

 

 

 

bullet

Electrics are all completed and certified by a local electrician

bullet

Ground floor Shower & WC and 1st floor WC are also installed and working

bullet

The hot water heating system is up and running

bullet

Plaster board has been completed throughout

bullet

All ground floor tiling, upstairs flooring and all ceilings are finished

bullet

Painting has begun one room of 6 complete ……………..

 

Work ongoing 

bullet

Internal painting to be finished and external rendering completed and painted 

bullet

Garden to be landscaped and fenced. Window shutters to be fitted

bullet

Kitchen to be installed this week and finally furniture, fittings and finishing touches.

 

 

 

As you can see from these photo's the gite is now taking shape ready for the arrival of our first guests!

 

 

 

 

 

 

AND last but by no means least ..................................................

 

A big THANKYOU to our family and friends for continued support and interest .

Thanks especially to Webmaster Dave and "The Plumbiere" here in France - we wouldn't have been able to get this far without your help. HONESTLY!

 

Click on the buttons below to view previous updates!

  

 
Home Page Reservations Self Catering The Gite offers Directions Photo Gallery Latest Updates Events